Boat Quay

Contracting

Largely untouched by the authorities for 30 odd years and festering with ad-hoc development. The 300m Boat Quay waterfront was overdue for an overhaul. The firm won the bid to deliver the project within budget in 9 months managing 4phases each lasting 6-8 weeks, in order to allow businesses to operate while construction was on-going.

My scope involved:
• Overall Project Schedule
• Site Management
• Integration of Arch/ Structure/ Mep
• Shop drawing production
• Material procurement , Mock ups and signs off
• Chairing Technical and Project Meetings
• Liaison design related matters with Consultants
• Defects rectification
• Stakeholder engagements and presentations

Boat Quay - Collapsible ORA

Tasked to design and build a collapsible outdoor shelter (Outdoor Refreshment Area) ORA to allow fire engines to make a U-turn. The firm went through several months of iterations before a full mock up was committed and built successfully.

Sketch Up model with shophouses

Collapsible ORA Perspective

Collapsible ORA Perspective

Collapsible ORA Built